[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-957024":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},957024,693,1,"单选题","水利水电工程可行性研究阶段引水隧洞线路工程地质测绘要求为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可选用比例尺1：5000～1：1000",false,{"key":16,"text":17,"correct":18},"B","可选用比例尺1：25000～1：5000",true,{"key":20,"text":21,"correct":14},"C","范围应为各比较线路及其两侧各300～500m",{"key":23,"text":24,"correct":14},"D","范围应为各比较线路及其两侧各100～500m","工程地质测绘比例尺：隧洞线路可选用1：25000～1：5000；地下厂房区可选用1：5000～1：1000。测绘范围应包括隧洞各比较线路及其两侧各300～1000m地带，测绘地质条件复杂地区时可适当扩大测绘范围。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]