[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-957023":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},957023,693,1,"单选题","水利水电工程可行性研究阶段引水隧洞及地下水厂房勘探平硐不应布置在( )等地段。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","隧洞进出口",false,{"key":16,"text":17,"correct":18},"B","洞顶上覆岩体最厚洞段",true,{"key":20,"text":21,"correct":14},"C","压力管道",{"key":23,"text":24,"correct":14},"D","地下厂房区","隧洞进出口、压力管道和地下厂房区可布置勘探平硐，并进行岩体的原位测试试验工作。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]