[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-957005":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},957005,693,1,"单选题","某水电站通过可行性研究阶段勘察，预测库周有一较大面积的农田区可能发生浸没。为查明该地段水文地质条件和工程地质条件，初步设计阶段按规定布置勘探剖面线，勘探剖面线上钻孔布置原则为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","钻孔间距应为200～500m，每个地貌单元钻孔不应少于2个，水库正常蓄水位线附近应布置钻孔，孔深应达到相对隔水层以下1m",false,{"key":16,"text":17,"correct":18},"B","钻孔间距应为500～1000m，每个地貌单元钻孔不应少于2个，水库正常蓄水位线附近应布置钻孔，孔深应达到相对隔水层以下1m",true,{"key":20,"text":21,"correct":14},"C","钻孔间距应为200～500m，每个地貌单元钻孔不应少于1个，水库正常蓄水位线附近应布置钻孔，孔深应达到相对隔水层以下1m",{"key":23,"text":24,"correct":14},"D","钻孔间距应为500～1000m，每个地貌单元钻孔不应少于1个，水库正常蓄水位线附近应布置钻孔，孔深应达到相对隔水层以下1m","根据《水利水电工程地质勘察规范》(GB50487—2008)第6.2.6.3条规定，初步设计阶段，水库浸没的勘察方法要求，勘探工作布置应符合的规定之一是：勘探剖面上的钻孔间距，农作物区应为500～1000m，建筑物区应为200～500m，剖面上每个地貌单元钻孔不应少于2个，水库正常蓄水位线附近应布置钻孔。钻孔深度应到达基岩或相对隔水层以下1m，钻孔内应测定稳定地下水位。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]