[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-957004":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},957004,693,1,"单选题","某水电站通过规划阶段地质调查，了解有一村屯位于正常蓄水位以上库岸附近，地形为向库内倾斜的缓坡，地表为较厚黏性土层，地下水位埋藏较浅并补给库内，当水库蓄水后可能存在( )工程地质问题。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","水库渗漏",false,{"key":16,"text":17,"correct":18},"B","水库浸没",true,{"key":20,"text":21,"correct":14},"C","水库坍剧",{"key":23,"text":24,"correct":14},"D","水库淹没","水库蓄水后，库区周围地下水相应壅高而接近或高于地面，导致地面农田盐碱化、沼泽化及建筑物地基条件恶化、矿坑涌水等，这种现象称为浸没。根据题目中给出的村屯的情况，可判断水库蓄水后可能存在水库淹没的工程地质问题。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]