[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-956987":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},956987,693,1,"单选题","规划阶段坝址区的工程地质测绘峡谷区应采用( )的比例尺。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1：5000～1：2000",false,{"key":16,"text":17,"correct":18},"B","1：10000～1：5000",true,{"key":20,"text":21,"correct":14},"C","1：25000～1：10000",{"key":23,"text":24,"correct":14},"D","1：50000～1：10000","根据《水利水电工程地质勘察规范》(GB50487—2008)，测绘的比例尺，峡谷区为1：10000～1：5000，丘陵平原区为1：25000～1：10000。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]