[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-956984":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},956984,693,1,"单选题","根据《水利水电工程地质勘察规范》(GB50487—2008)规定，可行性研究阶段峡谷河流坝址勘察时，各比选坝址应布置一条勘探剖面线，坝高( )m及以上的主要坝址，应在主要勘探剖面线上、下游增加辅助剖面线。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30",false,{"key":16,"text":17,"correct":14},"B","50",{"key":19,"text":20,"correct":21},"C","70",true,{"key":23,"text":24,"correct":14},"D","100","根据《水利水电工程地质勘察规范》(GB50487—2008)第5.4.2条规定，坝址勘探布置应符合的规定之一是：各比选坝址应布置一条主要勘探剖面。坝高70m及以上或地质条件复杂的主要坝址，应在主要勘探剖面上、下游布置辅助勘探剖面。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]