[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-956982":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},956982,693,1,"单选题","根据《堤防工程地质勘察规范》(SL188—2005)规定，对新建堤防下列哪项勘察工作应在初步设计阶段进行？( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对各堤线工程地质条件进行比较，对选定线路主要工程地质问题进行初步评价，并对堤线工程地质条件进行初步的分段评价",false,{"key":16,"text":17,"correct":18},"B","对地基的渗漏、渗透稳定、抗滑稳定、饱和砂土振动液化、振陷、沉陷变形等问题进行评价，并对堤线进行分段工程地质评价，提出处理措施的建议",true,{"key":20,"text":21,"correct":14},"C","基本查明基岩浅埋或出露区基岩的时代及岩性特征、岩层产状、风化程度、喀斯特发育特征、岩土接触面起伏变化情况等",{"key":23,"text":24,"correct":14},"D","对招标设计报告评审中要求补充论证的和施工中出现的工程地质问题进行勘察","除B项外，新建提防在初步设计阶段的勘察工作还包括：①查明堤基地质结构，特殊土层、粗粒土层以及腐殖土层、含沼气层等的分布、厚度及其性状；②查明基岩浅埋或出露区基岩的地层岩性，易风化、易软化、中等一强透水岩层的分布，断层破碎带、裂隙密集带的产状、规模、充填与胶结情况，岩土接触面的起伏变化情况等；③查明堤基土洞、喀斯特洞穴等的分布、规律、充填情况及充填物的形状，分析其对堤基渗漏、稳定的影响。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]