[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-956981":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},956981,693,1,"单选题","各规划梯级坝址的工程地质勘察应进行天然建筑材料( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","调查",false,{"key":16,"text":17,"correct":18},"B","普查",true,{"key":20,"text":21,"correct":14},"C","初查",{"key":23,"text":24,"correct":14},"D","详查","对天然建筑材料的普查以目测、目估为主，并辅以少量坑探。普查储量应不少于设计需要量的3倍。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]