[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-956972":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},956972,693,1,"单选题","初步设计阶段水利水电工程天然建筑材料勘察应( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","进行天然建筑材料初查",false,{"key":16,"text":17,"correct":14},"B","了解工程天然建筑材料赋存情况",{"key":19,"text":20,"correct":21},"C","进行天然建筑材料详查",true,{"key":23,"text":24,"correct":14},"D","复核前期工程天然建筑材料赋存情况","根据《水利水电工程地质勘察规范》(GB50487—2008)规定，初步设计阶段工程地质勘察的主要内容应包括：①查明水库区水文地质、工程地质条件，分析工程地质问题，预测蓄水后的变化；②查明建筑物区的工程地质条件并进行评价，为选定各建筑物的轴线及地基处理方案提供地质资料和建议；③查明导流工程的工程地质条件，根据需要进行施工附属建筑物场地的工程地质勘察和施工与生活用水水源初步调查；④进行天然建筑材料详查；⑤进行地下水动态观测和岩土体位移监测。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]