[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-956967":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},956967,693,1,"单选题","初步设计阶段拱坝坝肩及抗力岩体部位宜按( )布置平硐。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","每隔10～30m高差",false,{"key":16,"text":17,"correct":18},"B","每隔30～50m高差",true,{"key":20,"text":21,"correct":14},"C","每隔50～80m高差",{"key":23,"text":24,"correct":14},"D","每隔不超过100m高差","根据《水利水电工程地质勘察规范》(GB50487—2008)，拱坝坝肩每隔30—50m高程应有平硐控制。抗力体部位应布置专门的勘探，查明软弱岩体和缓倾角结构面。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]