[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-956966":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},956966,693,1,"单选题","初步设计阶段对主要坍岸区应进行详细勘察，其勘察的主要内容不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","岸坡的自然稳定坡角",false,{"key":16,"text":17,"correct":14},"B","浪击带稳定坡角",{"key":19,"text":20,"correct":14},"C","土的水下浅滩坡角",{"key":22,"text":23,"correct":24},"D","土的渗透系数",true,"除ABC三项外，初步设计阶段主要塌岸区进行详细勘察的主要内容还包括：①查明土的分层、级配和物理力学性质，预测不同库水位的塌岸范围，并提出长期观测的建议(预测中，应考虑水库的运用方式、风向和塌岸物质中粗颗粒的含量及其在坡角再沉积的影响；预测计算中，各阶段的稳定坡角应根据试验成果，结合调查资料选用)；②调查邻近地区已建水库库岸和相似地质条件的河湖岸的自然稳定坡角和浪击带稳定坡角；③查明防护工程区的工程地质条件。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]