[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-956959":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},956959,693,1,"单选题","针对水库存在的工程地质问题，开展专门性工程地质勘察工作应在( )阶剧进行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","可行性研究",false,{"key":16,"text":17,"correct":14},"B","预可行性研究",{"key":19,"text":20,"correct":21},"C","初步设计",true,{"key":23,"text":24,"correct":14},"D","施工详图设计","根据《水利水电工程地质勘察规范》(GB50487—2008)规定，初步设计阶段在可行性研究阶段勘察工作的基础上，针对水库存在的地质问题，开展专门性工程地质勘察工作。勘察内容包括水库渗漏、水库浸没、库岸稳定、水库诱发地震等工程地质问题。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]