[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-956958":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},956958,693,1,"单选题","在某流域河段上了解各梯级坝的工程地质条件，分析是否有建坝的可能性，应在( )阶段进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","规划",true,{"key":16,"text":17,"correct":18},"B","项目建议书",false,{"key":20,"text":21,"correct":18},"C","可行性研究",{"key":23,"text":24,"correct":18},"D","初步设计","根据《水利水电工程地质勘察规范》(GB50487—2008)规定，规划阶段工程地质勘察的主要内容包括：①了解规划河流或河段的区域地质和地震概况；②了解各梯级水库的地质条件和主要工程地质问题，分析建库的可能性；③了解各梯级坝址的工程地质条件，分析建坝的可能性；④了解长引水线路(长度大于2km的隧洞或渠道)的工程地质条件；⑤了解各梯级坝址附近的天然建筑材料的赋存情况。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]