[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-956955":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},956955,693,1,"单选题","溢洪道的工程地质勘察工作重点应放在初步设计阶段进行，工程地质测绘采用的比例尺一般为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1：500～1：1000",false,{"key":16,"text":17,"correct":18},"B","1：1000～1：2000",true,{"key":20,"text":21,"correct":14},"C","1：2000～1：5000",{"key":23,"text":24,"correct":14},"D","1：5000～1：10000","根据《水利水电工程地质勘察规范》(GB50487—2008)，进行测绘工作的方法和要求是：当溢洪道靠近坝体时，溢洪道的地面测绘可包括在坝址区工程地质测绘范围内。远离坝址的溢洪道是否要进行地面测绘应根据地形和地质复杂程度而定；如果为厚层的第四纪松散沉积物所覆盖，则可不做地面测绘工作。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]