[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-956953":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},956953,693,1,"单选题","可行性研究阶段工程地质勘察，对渠道的进出口和主要建筑物地段，应布置( )工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","坑探",false,{"key":16,"text":17,"correct":18},"B","钻探",true,{"key":20,"text":21,"correct":14},"C","工程物探",{"key":23,"text":24,"correct":14},"D","水文地质试验","可行性研究阶段工程地质勘察，对渠道的进出口和主要建筑物地段，应布置钻探工作，必要时取样进行试验分析。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]