[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-956950":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},956950,693,1,"单选题","可行性研究阶段对水库区可能存在渗漏地段应( )布置水文地质勘探剖面线。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","平行山坡",false,{"key":16,"text":17,"correct":14},"B","垂直山坡",{"key":19,"text":20,"correct":14},"C","垂直地下水流向或平行渗漏带",{"key":22,"text":23,"correct":24},"D","平行地下水流向或垂直渗漏带",true,"可行性研究阶段应在渗漏可疑地带进行勘探试验工作。勘探剖面垂直于地下水分水岭或平行于地下水流向布置，孔深应达到可靠的相对隔水层或喀斯特发育相对下限以下的适当深度。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]