[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-956934":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},956934,693,1,"单选题","下列( )不是在引水隧洞线路勘察中可行性研究阶段勘察报告应编写的内容。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","区域地质、各比较线路工程地质条件",false,{"key":16,"text":17,"correct":14},"B","主要的工程地质问题与方案选择",{"key":19,"text":20,"correct":14},"C","推荐线路的工程地质条件分段说明",{"key":22,"text":23,"correct":24},"D","查明主要工程地质问题并进行评价，提出处理意见",true,"D项，查明主要工程地质问题并进行评价，提出处理意见为初步设计工程阶段地质勘察工作。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]