[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-956883":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},956883,693,1,"单选题","",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","A—B",false,{"key":16,"text":17,"correct":14},"B","A—C",{"key":19,"text":20,"correct":21},"C","A—D",true,{"key":23,"text":24,"correct":14},"D","A—E","对A—B、A—C、A—D、A—E四条线进行比较。A—B线路较长，与最大主应力方向交角较大，约55°，与岩层交角约55°，线路通过两条断层、一条岩脉，岩石破碎，对洞线稳定不利，且出口条件一般。A—C、A—D线路较短，长度相差不大，但A—C线路穿过两条陡倾角断层，且与断层交角较小，近于平行，岩石可能破碎，对边墙稳定不利。A—C线路与最大主应力方向交角较大，约35°，与岩层交角约75°。A—D线路与最大主应力方向交角较小，约15°，与岩层走向近直交，交角约85°，线路虽穿过两条陡倾角断层，但近直交，距离较短，对洞线边墙稳定影响不大，该线路地质条件相对较好。A—E线路与A—D线路相比地质条件相差不大，但线路较长，且出口地质条件较差。",{"id":6,"name":27,"category":28,"favorite":29},"专业案例（水利水电）","建筑工程",0]