[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-954459":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},954459,692,1,"单选题","某项目由 A、 B、 C、D四个部分组成，当采用强制确定法进行价值工程对象选择时，它们的价值指数分别如下所示。其中不应作为价值工程分析对象的是：",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.7559",false,{"key":16,"text":17,"correct":18},"B","1.0000",true,{"key":20,"text":21,"correct":14},"C","1. 2245",{"key":23,"text":24,"correct":14},"D","1. 5071","提示 价值指数等于1说明该部分的功能与其成本相适应。",{"id":6,"name":27,"category":28,"favorite":29},"基础知识（水利水电）","建筑工程",0]