[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-954424":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},954424,692,1,"单选题","采用净现值指标对某项目进行财务盈利能力分析，设定的折现率为i，该项目财务上可行的条件是：",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","NPV≤企业可接受的水平",false,{"key":16,"text":17,"correct":14},"B","NPV",{"key":19,"text":20,"correct":21},"C","NPV≥0",true,{"key":23,"text":24,"correct":14},"D","NPV>i","提示 采用净现值指标的判定依据是净现值是否大于或等于0。",{"id":6,"name":27,"category":28,"favorite":29},"基础知识（水利水电）","建筑工程",0]