[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-954390":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},954390,692,1,"单选题","下面不属于工程建设其他投资的是：",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","土地使用费",false,{"key":16,"text":17,"correct":14},"B","与项目建设有关的其他费用",{"key":19,"text":20,"correct":21},"C","预备费",true,{"key":23,"text":24,"correct":14},"D","联合试运转费","提示 建设投资由工程费用(包括建筑工程费、设备购置费、安装工程费)，工程建设其他费用和预备费(包括基本预备费和涨价预备费)所组成。工程建设其他费用包括土地使用费、与项目建设有关的其他费用(包括建设单位管理费、研究试验费、勘察设计费、工程监理费、工程保险费、建设单位临时设施费、引进技术和设备进口项目的其他费用、环境影响评价费、劳动安全卫生评价费、特殊设备安全监督检验费、市政公用设施费)和与未来企业生产经营有关的费用(包括联合试运转费、生产准备费、办公和生活家具购置费)。",{"id":6,"name":27,"category":28,"favorite":29},"基础知识（水利水电）","建筑工程",0]