[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953829":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953829,691,2,"多选题","建设项目界面产生的原因包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","建设项目的复杂化",true,{"key":16,"text":17,"correct":14},"B","信息黏滞",{"key":19,"text":20,"correct":21},"C","经济冲突",false,{"key":23,"text":24,"correct":14},"D","专业化分工",{"key":26,"text":27,"correct":14},"E","目标差异","ABDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]