[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953826":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953826,691,2,"多选题","设计方项目管理的任务包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","与设计工作有关的安全管理",true,{"key":16,"text":17,"correct":14},"B","工程设计工作进度控制",{"key":19,"text":20,"correct":21},"C","与工程施工有关的组织与协调",false,{"key":23,"text":24,"correct":14},"D","工程设计质量控制",{"key":26,"text":27,"correct":14},"E","工程设计工作成本控制和与工程设计有关的建设项目工程造价控制","ABDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]