[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953808":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953808,691,2,"多选题","按照动态控制原理，在每一个投资动态控制过程中，项目管理人员的主要工作包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对投资目标计划值的分析和论证",true,{"key":16,"text":17,"correct":18},"B","编制相关质量控制报告",false,{"key":20,"text":21,"correct":14},"C","投资目标计划值与实际值的比较",{"key":23,"text":24,"correct":14},"D","项目投资偏差的分析",{"key":26,"text":27,"correct":14},"E","项目投资偏差纠正措施的采取","ACDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]