[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953803":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953803,691,2,"多选题","建设项目界面管理的共同模式和方法可归纳为( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","保持静界面的清楚界限",true,{"key":16,"text":17,"correct":18},"B","保持动界面的清楚界限",false,{"key":20,"text":21,"correct":18},"C","管理的注意力应放在跨越界面时的检查、监督和整体效益上",{"key":23,"text":24,"correct":14},"D","协调与处理具有相互依存关系的动界面，对于每个主要的界面进行特殊管理",{"key":26,"text":27,"correct":14},"E","划分建设项目的子系统，识别主导子系统的界面并能成功地处理其相互作用，应注意区分静界面和动界面，以便重点控制","ADE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]