[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953802":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953802,691,2,"多选题","建设项目的实施阶段可以划分为( )和保修阶段。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","设计准备阶段",true,{"key":16,"text":17,"correct":14},"B","设计阶段",{"key":19,"text":20,"correct":14},"C","施工阶段",{"key":22,"text":23,"correct":14},"D","动用前准备阶段",{"key":25,"text":26,"correct":27},"E","决策阶段",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]