[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953801":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953801,691,2,"多选题","在建设项目价值工程正式研究阶段，按照通常的价值工程研究活动计划，可分为( )、收集信息等步骤。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","方案创造",true,{"key":16,"text":17,"correct":14},"B","方案分析",{"key":19,"text":20,"correct":14},"C","方案发展与评价",{"key":22,"text":23,"correct":24},"D","建立费用模型",false,{"key":26,"text":27,"correct":14},"E","最终提案","ABCE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]