[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953794":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953794,691,2,"多选题","在项目前期和设计阶段，质量目标计划值和实际值的比较主要包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","技术设计和初步设计的比较",true,{"key":16,"text":17,"correct":18},"B","设备质量和设计要求的比较",false,{"key":20,"text":21,"correct":18},"C","材料质量和施工图设计要求的比较",{"key":23,"text":24,"correct":14},"D","初步设计和可行性研究报告、设计规范的比较",{"key":26,"text":27,"correct":14},"E","施工图设计和技术设计或初步设计、设计规范的比较","ADE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]