[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953793":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953793,691,2,"多选题","在施工图设计阶段，项目投资控制的主要任务是以被批准的设计概算为控制目标，应用( )等方法，以设计概算控制施工图设计工作的进行。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","限额设计",true,{"key":16,"text":17,"correct":14},"B","价值工程",{"key":19,"text":20,"correct":21},"C","工程计量",false,{"key":23,"text":24,"correct":21},"D","工程变更控制",{"key":26,"text":27,"correct":21},"E","设计标准与标准设计","AB","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]