[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953784":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953784,691,2,"多选题","在项目采购和施工阶段，投资目标计划值和实际值的比较主要包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","竣工决算价和设计概算的比较",true,{"key":16,"text":17,"correct":14},"B","工程结算价和施工合同价的比较",{"key":19,"text":20,"correct":21},"C","修正概算和设计概算的比较",false,{"key":23,"text":24,"correct":14},"D","工程结算价和资金使用计划(月\u002F季\u002F年或资金分块)的比较",{"key":26,"text":27,"correct":14},"E","资金使用计划(月\u002F季\u002F年或资金分块)和设计概算的比较","ABDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]