[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953781":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953781,691,2,"多选题","在建设项目价值工程研究准备阶段应该完成的工作有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","收集信息和进行功能分析",false,{"key":16,"text":17,"correct":18},"B","召开动员会",true,{"key":20,"text":21,"correct":18},"C","确定价值工程研究的地点和环境条件",{"key":23,"text":24,"correct":18},"D","成本或费用的分析，准备有关的模型和数据",{"key":26,"text":27,"correct":18},"E","选择参与价值工程研究的人员，组建价值工程研究小组","BCDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]