[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953780":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953780,691,2,"多选题","为实施工程进度目标的动态控制，项目管理人员的工作包括的主要方面有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","投资目标计划值与实际值的比较",false,{"key":16,"text":17,"correct":18},"B","协调进度计划执行过程中的问题",true,{"key":20,"text":21,"correct":18},"C","采集、汇总和分析实际进度数据",{"key":23,"text":24,"correct":18},"D","定期进行进度计划值和实际值的比较",{"key":26,"text":27,"correct":18},"E","如发现偏差，采取进度调整措施或调整进度计划","BCDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]