[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953774":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953774,691,2,"多选题","建设项目总承包方项目管理的目标为( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","质量目标，即项目的质量目标",true,{"key":16,"text":17,"correct":14},"B","进度目标，即项目的进度目标",{"key":19,"text":20,"correct":21},"C","进度目标，即工程设计工作的进度目标和建设项目的进度目标",false,{"key":23,"text":24,"correct":14},"D","费用目标，包括项目的总投资目标和建设项目总承包方的成本目标",{"key":26,"text":27,"correct":21},"E","投资目标，包括工程设计工作的成本目标和建设项目的投资目标","ABD","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]