[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953759":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953759,691,2,"多选题","项目管理信息系统的进度控制子系统的基本功能包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","绘制网络图",true,{"key":16,"text":17,"correct":18},"B","投资估算与项目概算的对比分析",false,{"key":20,"text":21,"correct":14},"C","实际进度与计划进度的动态比较",{"key":23,"text":24,"correct":14},"D","提供多种(不同管理平面)工程进度报表",{"key":26,"text":27,"correct":14},"E","编制双代号网络计划(CPM)和单代号搭接网络计划(MPM)","ACDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]