[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953755":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953755,691,2,"多选题","建设项目的投资项编码并不是概预算定额确定的分部分项工程的编码，它应综合考虑( )等因素，建立统一的编码，以服务于项目投资目标的动态控制。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","标底",true,{"key":16,"text":17,"correct":14},"B","概算、预算",{"key":19,"text":20,"correct":21},"C","决算",false,{"key":23,"text":24,"correct":14},"D","合同价",{"key":26,"text":27,"correct":14},"E","工程款的支付","ABDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]