[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953699":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953699,691,2,"多选题","施工总承包管理与施工总承包模式的不同体现在( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作开展程序不同",true,{"key":16,"text":17,"correct":18},"B","业主不同",false,{"key":20,"text":21,"correct":14},"C","对分包单位的选择和认可权限不同",{"key":23,"text":24,"correct":14},"D","对分包单位的付款方式不同",{"key":26,"text":27,"correct":14},"E","施工总承包管理的合同计价方式不同","ACDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]