[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953693":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953693,691,2,"多选题","根据CM模式的特点，CM模式主要适用于( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","时间要求紧迫的建设工程",true,{"key":16,"text":17,"correct":18},"B","时间要求相对宽裕的建设工程",false,{"key":20,"text":21,"correct":14},"C","设计变更可能性较大的建设工程",{"key":23,"text":24,"correct":18},"D","设计变更可能性不大的建设工程",{"key":26,"text":27,"correct":14},"E","项目范围和规模不确定而无法准确定价的建设工程","ACE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]