[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953690":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953690,691,2,"多选题","在建设项目决策和实施阶段，关于建设项目的技术、经济、管理和组织的规划、协调和控制等的具体工作主要由项目管理单位完成，建设项目业主的主要任务具体有( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","负责项目报批",true,{"key":16,"text":17,"correct":14},"B","负责实施过程中的有关决策",{"key":19,"text":20,"correct":14},"C","提出项目概念和构思，目的和要求",{"key":22,"text":23,"correct":14},"D","负责项目定义和项目实施方案等的决策",{"key":25,"text":26,"correct":27},"E","参加调试，组织装置性能考核、验收",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]