[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953681":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953681,691,2,"多选题","业主方委托项目管理与采用项目总控的组织模式是不同的，其区别有( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","地位不同",true,{"key":16,"text":17,"correct":14},"B","指令权不同",{"key":19,"text":20,"correct":14},"C","具体工作不同",{"key":22,"text":23,"correct":14},"D","工作特点不同",{"key":25,"text":26,"correct":27},"E","工作属性不同",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]