[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953677":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953677,691,2,"多选题","项目管理单位在建设项目施工阶段，负责( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对承包商进行全面管理",true,{"key":16,"text":17,"correct":18},"B","对投标商进行资格预审",false,{"key":20,"text":21,"correct":14},"C","参加调试，组织装置性能考核、验收",{"key":23,"text":24,"correct":14},"D","向建设项目业主移交项目全部文件资料",{"key":26,"text":27,"correct":14},"E","配合建设项目业主进行生产准备","ACDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]