[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953673":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953673,691,2,"多选题","CM\u002F非代理型模式合同结构的特征主要包括( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","由于业主对工程费用不能直接控制，有很大风险",true,{"key":16,"text":17,"correct":14},"B","CM单位与设计单位之间没有合同关系",{"key":19,"text":20,"correct":14},"C","CM合同形式一般采用\"成本+利润\"方式",{"key":22,"text":23,"correct":24},"D","CM合同需要等施工图完成后才签订",false,{"key":26,"text":27,"correct":14},"E","CM单位对各分包商的资格预审、招标、议标以及签约，都必须经过业主的确认才有效","ABCE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]