[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953665":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953665,691,2,"多选题","PMC单位在项目招标投标阶段，代表或协助建设项目业主主要进行的工作包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","配合建设项目业主进行生产准备",false,{"key":16,"text":17,"correct":18},"B","对建设项目总承包单位(如有)、施工或供货单位进行资格预审",true,{"key":20,"text":21,"correct":18},"C","编制建设项目总承包单位(如有)、施工或供货招标文件",{"key":23,"text":24,"correct":18},"D","主持或参与招投标和评标组织工作",{"key":26,"text":27,"correct":18},"E","协助建设项目业主与建设项目总承包单位(如有)、施工或供货中标单位进行合同谈判与签约","BCDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]