[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953661":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953661,691,2,"多选题","项目管理单位在建设项目设计阶段，负责( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","编制各个设计阶段的设计要求文件",true,{"key":16,"text":17,"correct":14},"B","进行风险分析并制定管理策略",{"key":19,"text":20,"correct":14},"C","协助建设项目业主选择专利技术",{"key":22,"text":23,"correct":14},"D","审查专利商提供的工艺包设计文件",{"key":25,"text":26,"correct":27},"E","编制并发布工程施工应统一遵循的标准、规范和规定",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]