[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953652":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953652,691,2,"多选题","项目结构分解并没有统一的模式，但应结合项目的特点和参考( )的原则进行。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","考虑项目的组成",true,{"key":16,"text":17,"correct":14},"B","有利于项目目标的控制",{"key":19,"text":20,"correct":21},"C","仅考虑项目进展的局部部署",false,{"key":23,"text":24,"correct":14},"D","结合项目管理的组织结构",{"key":26,"text":27,"correct":14},"E","有利于项目实施任务(设计、施工和物资采购)的发包和有利于项目实施任务的进行，并结合合同结构","ABDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]