[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953646":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953646,691,2,"多选题","一个建设项目在( )的组织系统(相对于软件和硬件而言，组织系统也可称为组织件)不仅包括建设单位本身的组织系统，还包括各参与单位共同或分别建立的针对该工程项目的组织系统。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","决策阶段",true,{"key":16,"text":17,"correct":14},"B","实施阶段",{"key":19,"text":20,"correct":14},"C","运营阶段",{"key":22,"text":23,"correct":24},"D","分析评价阶段",false,{"key":26,"text":27,"correct":24},"E","准备阶段","ABC","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目组织","建筑工程",0]