[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953640":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},953640,691,1,"单选题","在竣工验收阶段，项目投资控制的主要任务是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","以工程设计文件为依据，结合工程施工的具体情况，参与招标文件的制定",false,{"key":16,"text":17,"correct":18},"B","全面汇集在工程建设过程中实际花费的全部费用，编制竣工决算",true,{"key":20,"text":21,"correct":14},"C","以被批准的设计概算为控制目标，应用限额设计、价值工程等方法，以设计概算控制施工图设计工作的进行",{"key":23,"text":24,"correct":14},"D","以施工图预算、工程施工承包合同价等为控制依据，通过工程计量、工程变更控制等方法，按照承包方实际完成的工程量，严格确定施工阶段实际发生的工程费用","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目组织","建筑工程",0]