[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953628":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},953628,691,1,"单选题","采取调整项目组织结构、任务分工、管理职能分工、工作流程组织和项目管理班子人员等措施属于目标控制纠偏措施中的( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","管理措施",false,{"key":16,"text":17,"correct":14},"B","技术措施",{"key":19,"text":20,"correct":21},"C","组织措施",true,{"key":23,"text":24,"correct":14},"D","经济措施","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目组织","建筑工程",0]