[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953620":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},953620,691,1,"单选题","在价值工程研究活动中，最重要的阶段是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","收集信息与功能分析",false,{"key":16,"text":17,"correct":14},"B","研究前的准备",{"key":19,"text":20,"correct":14},"C","方案创造与评价",{"key":22,"text":23,"correct":24},"D","方案发展与提案形成",true,"",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目组织","建筑工程",0]