[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953607":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},953607,691,1,"单选题","在项目决策阶段，项目投资控制的主要任务是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","根据拟建项目的功能要求和使用要求，做出项目定义，包括项目投资定义",true,{"key":16,"text":17,"correct":18},"B","全面汇集在工程建设过程中实际花费的全部费用，编制竣工决算",false,{"key":20,"text":21,"correct":18},"C","应以被批准的设计概算为控制目标，应用限额设计、价值工程等方法，以设计概算控制施工图设计工作的进行",{"key":23,"text":24,"correct":18},"D","运用设计标准与标准设计、价值工程方法、限额设计方法等，以可行性研究报告中被批准的投资估算为投资控制计划值，对初步设计工作进行控制","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目组织","建筑工程",0]