[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953601":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},953601,691,1,"单选题","判断有无投资偏差的基础是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","各类投资控制报告和报表的制定",false,{"key":16,"text":17,"correct":14},"B","投资目标计划值与实际值的比较",{"key":19,"text":20,"correct":21},"C","项目投资实际数据的及时、完整和正确",true,{"key":23,"text":24,"correct":14},"D","项目投资偏差纠正措施的采取","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目组织","建筑工程",0]